51.
FortisBC Energy Inc. (Re) - 2017-07-20
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On June 21, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission) pursuant to section 50(3) of the Utilities Commission Act for approval of the following: ...
-
52.
FortisBC Energy Inc. (Re) - 2017-07-18
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On December 19, 2016, FortisBC Energy Inc. (FEI) filed its 2016 Rate Design Application with the British Columbia Utilities Commission (Commission) and on February 2, 2017, FEI provided a supplemental...
-
53.
Pacific Northern Gas (N.E.) Ltd. (Re) - 2017-06-27
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On February 24, 2017, Pacific Northern Gas (N.E.) Ltd. (PNG (N.E.) ) applied to the British Columbia Utilities Commission (Commission) for approval to record in the Fort St. John/Dawson Creek (FSJ/DC)...
-
54.
Pacific Northern Gas Ltd. (Re) - 2017-06-27
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On February 24, 2017, Pacific Northern Gas Ltd. (PNG) applied to the British Columbia Utilities Commission (Commission) for approval to record in the PNG-West service area unaccounted for gas (UAF) lo...
-
55.
FortisBC Energy Inc. (Re) - 2017-06-22
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On March 30, 2017, FortisBC Energy Inc. (FEI) filed with the British Columbia Utilities Commission (Commission) an application requesting an extension to the filing date of its long term gas resource ...
-
56.
FortisBC Energy Inc. (Re) - 2017-06-21
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On May 17, 2017, the City of Surrey applied to the British Columbia Utilities Commission (Commission) for an order pursuant to subsection 32(2) of the Utilities Commission Act (UCA) specifying the ter...
-
57.
FortisBC Energy Inc. (Re) - 2017-06-15
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On May 29, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to sections 59 to 61 of the Utilities Commission Act (UCA), for interim approval...
-
58.
Pacific Northern Gas (N.E.) Ltd. (Re) - 2017-06-15
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On June 7, 2017 Pacific Northern Gas (N.E.) Ltd. [PNG(N.E.)] filed with the British Columbia Utilities Commission (Commission) its 2017 Second Quarter Report on gas supply costs and Gas Cost Variance ...
-
59.
Sun Peaks Utilities Co., Ltd. (Re) - 2017-06-15
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On May 11, 2017, Sun Peaks Utilities Co., Ltd. (SPUCL) filed with the British Columbia Utilities Commission (Commission) a Gas Cost Reconciliation Account (GCRA) report, which includes actual and pro...
-
60.
FortisBC Energy Inc. (Re) - 2017-06-08
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On March 30, 2017, pursuant to section 71 of the Utilities Commission Act and Section 6.0 of the British Columbia Utilities Commission’s (Commission) Rules for Natural Gas Energy Supply Contracts that...
-
61.
Pacific Northern Gas Ltd. (Re) - 2017-06-08
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On April 11, 2017, pursuant to section 71 of the Utilities Commission Act and the British Columbia Utilities Commission’s (Commission) Rules for Natural Gas Energy Supply Contracts that are set out in...
-
62.
FortisBC Energy Inc. (Re) - 2017-05-26
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : FortisBC Energy Inc. (FEI) obtained a Certificate of Public Convenience and Necessity (CPCN) on August 14, 2006 for the Commodity Unbundling Project for Residential Customers (Customer Choice) in acco...
-
63.
FortisBC Energy Inc. (FEI) (Re) - 2017-05-25
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On April 10, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to sections 59 to 61 and 89 of the Utilities Commission Act (UCA), for interim...
-
64.
FortisBC Energy Inc. (Re) - 2017-05-17
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : A. On March 6, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to sections 59 to 61 of the Utilities Commission Act (UCA), for permanent ap...
-
65.
FortisBC Energy Inc. (Re) - 2017-05-17
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : A. On March 6, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to sections 59 to 61 of the Utilities Commission Act (UCA), for permanent ap...
-
66.
FortisBC Energy Inc. (Re) - 2017-05-17
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : A. On March 6, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to sections 59 to 61 of the Utilities Commission Act (UCA), for permanent ap...
-
67.Résumé : On November 10, 2016, FortisBC Inc. (FBC) filed with the British Columbia Utilities Commission (Commission) its Self-Generation Policy Stage II Application, seeking among other things, approval of the...
-
68.
FortisBC Energy Inc. (Re) - 2017-05-04
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On April 10, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to section 5 (1.2) of Order in Council (OIC) No. 162, for approval to amend R...
-
69.
FortisBC Energy Inc. (Re) - 2017-05-04
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On April 10, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to section 5 (1.2) of Order in Council (OIC) No. 162, for approval to amend Ra...
-
70.
FortisBC Energy Inc. (Re) - 2017-05-01
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On February 3, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to sections 59 to 61 of the Utilities Commission Act (UCA), for permanent ap...
-
71.
FortisBC Energy Inc. (Re) - 2017-05-01
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On February 3, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to sections 59 to 61 of the Utilities Commission Act (UCA), for permanent ap...
-
72.
FortisBC Energy Inc. (Re) - 2017-04-12
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On March 21, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission) for approval of rate treatment for Prescribed Undertakings 3.2 and 3.4, requesting a Com...
-
73.
FortisBC Energy Inc. (Re) - 2017-04-06
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On February 23, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission) for approval of the Operating Agreement dated January 30, 2017 (Operating Agreement)...
-
74.
FortisBC Energy Inc. (Re) - 2017-04-06
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On March 15, 2017, and later revised on March 28, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission) for approval of the Operating Agreement dated Janua...
-
75.
FortisBC Energy Inc (Re) - 2017-04-04
British Columbia Utilities Commission - Ordonnance [ Anglais ]Résumé : On June 30, 2016, FortisBC Energy Inc. (FEI) filed an application for the approval of its draft All-Inclusive Code of Conduct and Transfer Pricing Policy (CoC/TPP) (Application);