76.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by applications 23565-A001 to 23565-A007 registered on May 16, 2018, filed applications with the Alberta Utilities Commission under Section 12 of the Pipeline Act a...
-
77.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by Application 23551-A001 registered on May 10, 2018, filed an application with the Alberta Utilities Commission under Section 11 of the Pipeline Act and Section 4....
-
78.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by applications 23545-A001 to 23545-A014 registered on May 9, 2018, filed applications with the Alberta Utilities Commission under Section 11 of the Pipeline Act an...
-
79.Résumé : In this decision, the Alberta Utilities Commission must decide whether to approve an application from AltaGas Utilities Inc. for an amendment to Licence 210 for the addition of a new 11.2-kilometre lo...
-
80.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by Application 23550-A001 registered on May 10, 2018, filed an application with the Alberta Utilities Commission under Section 12 of the Pipeline Act and Section 4....
-
81.Résumé : On May 16, 2018, AltaGas Utilities Inc. (AltaGas) applied to the Alberta UtilitiesCommission for approval of a natural gas franchise agreement with the Summer Village ofCrystal Springs. The applicatio...
-
82.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by Application 23541-A001 registered on May 8, 2018, filed an application with the Alberta Utilities Commission under Section 11 of the Pipeline Act and Section 4.1...
-
83.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by Application 23526-A001 registered on April 30, 2018, filed an application with the Alberta Utilities Commission under Section 11 of the Pipeline Act and Section ...
-
84.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by Application 23524-A001 registered on April 27, 2018, filed an application with the Alberta Utilities Commission under Section 11 of the Pipeline Act and Section ...
-
85.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by Application 23490-A001 registered on
April 9, 2018, filed an application with the Alberta Utilities Commission under Section 11 of...
-
86.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by applications 23503-A001 to 23503-A004 registered on April 17, 2018, filed applications with the Alberta Utilities Commission under Section 12 of the Pipeline Act...
-
87.Résumé : For the reasons set out in this decision, the Alberta Utilities Commission approves the updated terms and conditions of service (updated T&Cs) proposed by AltaGas Utilities Inc. (AltaGas or AUI) in it...
-
88.
ATCO Pipelines (ATCO Gas and Pipelines Ltd.) (Re) - 2018-04-30
Alberta Utilities Commission - Décision [ Anglais ]Résumé : In this decision, the Alberta Utilities Commission considers applications (the costs claim applications) by ATCO Pipelines, a division of ATCO Gas and Pipelines Ltd. (ATCO Pipelines) and the Consumers...
-
89.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by Application 23491-A001 registered on April 10, 2018, filed an application with the Alberta Utilities Commission under Section 11 of
the Pipeline Act and Section ...
-
90.Résumé : On April 19, 2018, ATCO Gas and Pipelines Ltd. (ATCO Gas) applied to the Alberta Utilities Commission for approval of a natural gas franchise agreement with the Village of Wabamun. The application was...
-
91.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by Application 23480-A001 registered on April 5, 2018, filed an application with the Alberta Utilities Commission under Section 12 of the Pipeline Act and Section 4...
-
92.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by applications 23452-A001 and 23452-A003 registered on March 26, 2018, filed applications with the Alberta Utilities Commission under Section 12 of the Pipeline Ac...
-
93.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by Application 23450-A001 registered on March 26, 2018, filed an application with the Alberta Utilities Commission under Section 12 of the Pipeline Act and Section ...
-
94.
ATCO Gas and Pipelines Ltd. South (Re) - 2018-04-10
Alberta Utilities Commission - Décision [ Anglais ]Résumé : The Alberta Utilities Commission received your application dated April 4, 2018, for amendments to Rider A and a copy of the revised Rider A schedule for ATCO Gas South, attached as Appendix 1 to this ...
-
95.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by Application 23432-A001 registered on March 21, 2018, filed an application with the Alberta Utilities Commission under Section 12 of the Pipeline Act and Section ...
-
96.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by applications 23434-A001 and 23434-A002 registered on March 21, 2018, filed applications with the Alberta Utilities Commission under Section 12 of the Pipeline Ac...
-
97.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by applications 23501-A001 and 23501-A002 registered on April 16, 2018, filed applications with the Alberta Utilities Commission under Section 11 of the Pipeline Ac...
-
98.Résumé : On March 23, 2018, the Alberta Utilities Commission issued Decision 23355-D01-20181 regarding applications by each of AltaGas Utilities Inc., ATCO Electric Ltd., ATCO Gas and Pipelines Ltd., ENMAX Pow...
-
99.Résumé : On March 20, 2018, the Alberta Utilities Commission issued Disposition 23421-D012018. By letter dated March 27, 2018, AltaGas Utilities Inc. (AltaGas) advised the Commission of an administrative error...
-
100.Résumé : ATCO Gas and Pipelines Ltd. (ATCO), by Application 23422-A001 registered on March 15, 2018, filed an application with the Alberta Utilities Commission under Section 11 of the Pipeline Act and Section ...