Supreme Court

Decision Information

Decision information:

Transcript of the Decision

Decision Content

Porter v. Beck, 2017 NWTSC 12 S-1-CV-2013-000043 IN THE SUPREME COURT OF THE NORTHWEST TERRITORIES BETWEEN: BLAIR PORTER Plaintiff(s)

- and - (1) RODNEY R. BECK and (2) JANELLE D. BECK Defendant(s)

_________________________________________________________ Transcript of the Decision by The Honourable Justice A. M. Mahar, sitting in Hay River, in the Northwest Territories, on the 27th day of January, 2017. _________________________________________________________

APPEARANCES: Mr. B. Porter: Appearing on behalf of the Plaintiff Mr. R. Beck: Appearing on behalf of the Defendants Ms. J. Beck: Appearing on behalf of the Defendants

Official Court Reporters

1 THE COURT: We held a trial this week 2 between Blair Porter, the plaintiff and defendant 3 on the counterclaim, and Rodney and Jenelle Beck, 4 defendants on the original claim and plaintiffs 5 on the counterclaim. 6 In October of 2012 the Becks entered into 7 a contract with Blair Porter for a complete 8 renovation of their basement. This included 9 a bathroom, a laundry room, two bedrooms, 10 and a total price of $45,000 was agreed upon. 11 This $45,000 included all materials, as well 12 as a $6,300 value set aside for unforeseen 13 costs. Work began. Everything was going 14 well initially. Two progress payments of 15 $11,000 each were made. The Becks also 16 supplied $12,000 worth of materials. 17 Around Christmas, while the Becks were 18 having a child, Mr. Porter found himself in 19 fairly desperate circumstances and he asked 20 for a further progress payment; the Becks 21 provided a further $5,000. Adding the $12,000, 22 $22,000 and $5,000 together, there was $6,000 23 remaining on the contract. The contract was 24 inclusive of tax. 25 In early February, while the work was 26 still incomplete, and I will get into that in 27 more detail soon, Mr. Porter asked, depending

Official Court Reporters 1

1 on the evidence, either for full payment or 2 for a further $5,000. Whichever it was, $5,000 3 was close enough to the final amount remaining 4 that it could be considered essentially a final 5 payment. The Becks said no, that they wanted 6 to wait until the work was done or at least 7 more substantially complete. 8 Mere days later they were served with 9 a final bill, which included $6,000 for the 10 remainder of the contract, $971 for miscellaneous 11 work relating to the work on the contract, and 12 $525 for the upstairs demolition. The upstairs 13 demolition was an interesting issue. It may 14 or may not have been agreed to by the parties. 15 In any event, I propose to deal with it by way 16 of an offset against the cost that was required 17 to at least clean up the upstairs and make it 18 habitable. The total value that was claimed by 19 Mr. Porter was $7,656. The Becks counterclaimed, 20 claiming that there were substantial deficiencies 21 in the work that was done, as well as work that 22 was simply not done, and are asking for a total 23 of $37,000. 24 During testimony Mr. Porter originally 25 suggested that the work was complete to the 26 state required under the contract. Over the 27 course of the trial he did agree that there

Official Court Reporters 2

1 were deficiencies and that there were also 2 things that should have been done that were 3 not done. 4 I make the following findings: I find that 5 Mr. Porter has not met the burden with respect 6 to his claim and there will be no judgement in 7 his favour accordingly. There will be an offset, 8 which I will discuss again shortly. I find that 9 the Becks have succeeded in their claim on a 10 balance of probabilities, but not to the extent 11 of the originally claimed amount, and I will 12 now go into the details of that. 13 I find that the work was below the 14 minimum acceptable standard in a number of 15 ways, and again, Mr. Porter was candid about 16 this. He was going through a difficult time 17 towards the end of the contract, and work that 18 likely would have been done in a better way 19 by him simply was not. The staircase was 12 20 inches below code, a substantial amount below 21 code. It was 65 inches, the code mandated 77 22 inches. The Becks attempted to repair this 23 through another contractor afterwards at a 24 cost of $5,000, but they were still four inches 25 out of code. So the staircase is going to have 26 to be replaced. The staircase itself was poorly 27 constructed. There were obvious cracks along

Official Court Reporters 3

1 stress points basically along the entire length 2 of the staircase. I am not going to make a 3 judicial finding that these cracks were caused 4 only by stress on the staircase, but whether 5 it was caused by stress on the staircase or by 6 cracking due to the heat from the wood stove, 7 all of that was known to Mr. Porter when he 8 constructed the staircase and it should have 9 been better built. So for both of those reasons, 10 one because of the code, and two because of the 11 construction of the staircase, the staircase 12 is going to have to be completely rebuilt. 13 Mr. Beck was candid when he stated that 14 he could not recall whether or not a railing 15 was part of the original discussion. I gave 16 Mr. Porter the benefit of the doubt on that 17 and I accordingly deducted the cost of the 18 railing. 19 A drop-down ceiling was placed throughout 20 by a subcontractor. It is an extensive piece 21 of work involving plaster work on an existing 22 ceiling. The ceiling apparently was attached 23 to strapping that was not dry. The strapping 24 appears to have shrunk and cracked along the 25 seams in the gyproc. I do not believe Mr. Porter 26 is objecting to that conclusion, it is simply a 27 question of what needs to be done to fix it. But

Official Court Reporters 4

1 it needs to be fixed. As well, there are visible 2 deficiencies in the walls, there are deficiencies 3 in the trim and deficiencies in the electrical 4 outlets. It is all relatively minor work, but 5 it is all going to have to be done, and there 6 is going to have to be some substantial work 7 done. We have a quote on that, which I will 8 get to shortly, but that was another deficiency. 9 In the bathroom the toilet was placed 10 six inches too far from the wall, which is 11 not only unsightly, but is actually a bit of 12 a hazard because it can then crack. The floor 13 was not level, resulting in a one-inch gap at 14 one end, or probably a little greater than a 15 one-inch gap at the one end of the tub, which 16 is also not acceptable. The tile also did not 17 meet the vanity which was eventually put in. 18 As this vanity was supplied by the Becks I am 19 not proposing to give value for the original 20 custom vanity that was agreed upon, but the 21 tile work still needs to be redone. The tile 22 work needs to be redone, the floor needs to 23 be levelled, and the toilet needs to be moved. 24 There is also an open unfinished space that 25 should have been filled in the closet, which 26 needs to be addressed. 27 In the laundry room there is an open

Official Court Reporters 5

1 unfinished space which needs to be at the 2 very least drywalled and taped and mudded. 3 There also needs to be a shelf in the closet 4 and a vent cover placed on an open heating 5 vent. Both bedrooms require shelves in the 6 closets. There also needs to be some work 7 done in terms of making safer hatches into 8 the plumbing access ports in the flooring. 9 Upstairs there appears to have been a 10 misunderstanding with respect to the demolition 11 of a wall. That said, the upstairs was left in 12 a totally unsatisfactory state for habitation. 13 There were protruding nails, exposed live wires, 14 which, while they were maretted off at least, 15 were not in any way left safe. Work had to 16 be done to correct that and we have a number 17 attached to that as well. 18 There was substantial garbage left outside 19 by way of waste. Now, this was not unexpected, 20 but given the way the relationship between the 21 parties went that waste was left at the end in 22 the wintertime and had to be dealt with when 23 the weather cleared. 24 There was an issue with respect to the 25 amount of finish that was done in the wood 26 room. It was not clear to me exactly what 27 had been agreed on between the parties in

Official Court Reporters 6

1 the contract. Probably something more should 2 have been done, but I am not proposing to attach 3 any dollar figure to that, just because it was 4 unclear exactly what should have been done. 5 Given the nature of the work that was 6 done, it was entirely reasonable for the 7 Becks to withhold the final payment until a 8 more substantial completion had been reached. 9 Virtually all of the money that was required 10 had already been paid. They were simply left 11 with about 13 to 15 percent of the outstanding 12 bill remaining, and as I said, it was entirely 13 reasonable for them to withhold that final 14 payment until completion of the work. 15 I take Mr. Porter at his word when he 16 says he would have remedied everything, but 17 given the way the relationship between the 18 parties went after the filing of the lien 19 it would be completely unreasonable to expect 20 that the Becks would have been content with 21 him coming in to do the work. So we are going 22 to have to look at the costs to get other people 23 to remedy the deficiencies in the undone work. 24 In terms of Mr. Porter's claim, while 25 I have rejected the basis for the claim, there 26 was an agreed upon amount of $45,000 for the 27 completion of the work. Since I am going to

Official Court Reporters 7

1 be imposing judgement against Mr. Porter for 2 the completed work it is only fair that I deduct 3 the cost to completion that was contemplated by 4 the contract. 5 So there will be a $6,000 credit against the 6 amount that I am going to award, which brings us 7 to the $45,000. Because of the misunderstanding 8 with respect to the work upstairs there will be a 9 $525 credit to Mr. Porter as against the roughly 10 $1,250 that it cost to get the work upstairs put 11 in a condition where you could use the house. 12 The $971 that was claimed for miscellaneous 13 work should have been included in the $6,300 14 that was set aside in the contract. So I do 15 not credit the $971, I simply reject it. So 16 the total amount of offset will be $6,525. 17 In terms of damages, for the cleanup we 18 heard from Chris Betts from Arcan, which is 19 perhaps the premier contracting firm in town. 20 They typically do commercial work, but they 21 also do some residential work. The original 22 quote was quite high, but it involved the use 23 of a dumpster and also the need to remove the 24 materials during the wintertime. Mr. Betts 25 agreed that a reasonable amount or the minimum 26 amount to remove those materials was a thousand 27 dollars. I will impose judgement for a thousand

Official Court Reporters 8

1 dollars with respect to the cleanup. 2 With respect to the bathroom, we received 3 a very reasonable quote from Mr. Betts in terms 4 of levelling the floor, moving the plumbing and 5 fixing the tile work around the vanity that is 6 currently in place of $2,500. I see no reason 7 to deviate from that $2,500 and that amount is 8 imposed as well. 9 With respect to the staircase the quote 10 was $8,740. There was a 25 percent acknowledged 11 reduction for that work to be done by a more 12 standard contractor here in town. I take that 13 into account, that the contract with Mr. Porter 14 contemplated someone like Mr. Porter doing the 15 work, and it would not be fair to Mr. Porter 16 to impose the cost of having the highest priced 17 contractor in town doing the work. There is 18 also a 25 percent reduction, which I take from 19 that amount, from the 25 percent already reduced 20 amount for the railing, which leaves an amount 21 just shy of $5,000. I will raise that to $5,000 22 simply in fairness. There is going to be some 23 additional work that needs to be done and it 24 is only a matter of about $70, which is the 25 difference between $5,000 and the amount 26 I came to. So $5,000 for the staircase. 27 To fix the sealing and do the necessary

Official Court Reporters 9

1 painting and patch-up, we heard from Andrey 2 Dziewa. To completely redo the paint work 3 and plaster work in the basement up to the 4 standard that Mr. Dziewa, a professional painter, 5 would have done it, and it was quoted at $5,040. 6 Mr. Dziewa agreed that if he was only going to do 7 what was necessary to bring it up to a reasonable 8 standard that the amount would be roughly half of 9 that at $2,500. Therefore, there will be $2,500. 10 He said between $2,000 and $2,500. There is an 11 extensive amount that needs to be done, so we 12 will make it $2,500. 13 Moving onto the cabinets in the bathroom, 14 we heard from Mr. Lafferty. A cabinet is going 15 to be $475. That seems like a fair amount, I 16 will impose that. Shelves in the two bedrooms 17 and the one shelf in the laundry room came to 18 a further $400, for a total of $875. 19 With respect to the open space in the 20 laundry room, I used my own discretion in 21 terms of coming to a number on that, with 22 respect to gyproc and a vent cover, of $200. 23 So I add $200 to the amount for that piece 24 of work. 25 Upstairs, a total of $1,250 was spent, 26 which seems quite reasonable to bring the 27 upstairs to a state that was safe and usable.

Official Court Reporters 10

1 I will apply the $1,250 as well, for a total 2 of $13,325. I take $13,325 and subtract $6,525. 3 I am left with an amount of $6,800. So there 4 is judgement against Mr. Porter in the amount 5 of $6,800 even. 6 I make the following orders: The lien 7 against 5 Mackie Place, Hay River, Northwest 8 Territories, legal description lot 905, plan 9 380, Hay River, taken out by Mr. Porter, is 10 to be removed. The Becks will have judgement 11 against Mr. Porter in the amount of $6,800. 12 I will impose costs in favour of the Becks 13 on a party and party basis. 14 Madam Clerk, is there anything I have 15 neglected that you can think of? 16 THE CLERK: I don't believe so, Your 17 Honour. 18 THE COURT: Is there anything from 19 either one of the parties in terms of anything 20 I have forgotten? 21 MR. BECK: The window wells you never 22 spoke about, but I don't know if you just threw 23 that out. 24 THE COURT: With respect to the window 25 wells, my understanding was that the work on 26 the exterior of the house was to be completed 27 as part of another contract, and that was not

Official Court Reporters 11

1 substantially deviated from in the testimony. 2 It was sloppy leaving the cracks in them, but 3 I do not see any reason to impose anything 4 further for that. 5 MR. BECK: Okay. 6 THE COURT: I did think about it. 7 Again, I want to thank you all the way this 8 went this week. 9 MR. BECK: Thank you. 10 THE COURT: And hopefully you can all 11 put it behind you. I wish you all the best. 12 Close court. 13 ----------------------------- 14 15 Certified to be a true and accurate transcript, pursuant 16 to Rules 723 and 724 of the Supreme Court Rules. 17

18 _____________________________ 19 Joel Bowker Court Reporter 20

21 22 23 24 25 26 27

Official Court Reporters 12

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.