Facts

  • The case involves Southwestern Public Service Company's (SPS) appeal against the New Mexico Public Regulation Commission's (PRC) denial of its application for a financial incentive under the Renewable Energy Act (REA). SPS proposed to retire banked renewable energy certificates (RECs) early to exceed the Renewable Portfolio Standard (RPS) requirements, seeking a financial incentive for this action. The PRC denied the application, concluding that SPS's proposal did not meet the statutory requirement of producing or acquiring renewable energy to qualify for an incentive (paras 1-3, 11-13).

Procedural History

  • The PRC approved the Amended Rule in April 2021, after an eighteen-month rulemaking process. SPS appealed this order, alleging legal infirmities (para 9).
  • SPS filed an application with the PRC under the REA and the Amended Rule, seeking approvals for its 2022 Annual Renewable Energy Act Plan and several proposed rate riders. This application included a request for a financial incentive, which was later denied by the PRC in December 2021. SPS appealed this denial, and the appeal was consolidated with the pending appeal challenging the Amended Rule (paras 10-15).

Parties' Submissions

  • Appellant (SPS): Argued that the PRC's interpretation of the REA to deny the financial incentive was arbitrary and capricious, contrary to law, and an abuse of discretion. SPS contended that retiring RECs early to exceed the RPS should qualify for an incentive under the REA. SPS also challenged various provisions of the Amended Rule as exceeding the scope of the REA, being arbitrary, capricious, void for vagueness, and adopted without proper notice and comment (paras 17, 25, 34-35, 39, 45-46, 47-48, 49-52, 53-54, 55, 57, 59-61).
  • Appellee (PRC): Defended its interpretation of the REA and the legality of the Amended Rule, arguing that SPS's proposal to retire banked RECs did not meet the statutory requirement of producing or acquiring renewable energy. The PRC also contended that the challenged provisions of the Amended Rule were within its authority to implement the REA and ensure reasonable and proper services at fair rates (paras 18-24, 36-44).

Legal Issues

  • Whether the PRC's denial of SPS's application for a financial incentive under the REA was reasonable and lawful (para 17).
  • Whether various provisions of the Amended Rule exceed the scope of the REA, are arbitrary and capricious, void for vagueness, or were adopted without proper notice and comment (paras 34-61).

Disposition

  • The PRC's orders adopting the Amended Rule and denying SPS's 2021 request for a financial incentive were affirmed in all respects (para 63).

Reasons

  • The court held that SPS's proposal to retire banked RECs early did not qualify for an incentive under the REA because it did not involve producing or acquiring renewable energy. The court found the PRC's interpretation of the REA and its adoption of the Amended Rule to be within its authority, reasonable, and lawful. The court also addressed and rejected SPS's challenges to various provisions of the Amended Rule, finding them either moot or without merit (paras 18-61).