Facts

  • Resolute Wind 1 LLC (Resolute Wind) filed a complaint against Lea County Electric Cooperative, Inc. (Lea County Electric) and Western Farmers Electric Cooperative, Inc. (Western Farmers Electric), asserting it is a "qualifying facility" under the Public Utility Regulatory Policies Act of 1978 (PURPA) and entitled to have Lea County Electric purchase its energy and capacity. Resolute Wind argued that Lea County Electric could not transfer its purchase obligation to Western Farmers Electric without Resolute Wind's consent, which had not been given. The dispute centered on whether Lea County Electric had a "full-requirements contract" with Western Farmers Electric and whether such a contract could transfer the purchase obligation without Resolute Wind's consent (paras 9-12).

Procedural History

  • [Not applicable or not found]

Parties' Submissions

  • Appellant (Resolute Wind): Argued that it is a qualifying facility under PURPA and that Lea County Electric is obligated to purchase its energy and capacity. Contended that Lea County Electric could not transfer its purchase obligation to Western Farmers Electric without Resolute Wind's consent, which was not given. Disputed the application of avoided costs and the method for calculating them (paras 10-12).
  • Appellee (New Mexico Public Regulation Commission): [Not applicable or not found]
  • Intervenor-Appellee (Lea County Electric Cooperative, Inc. and Western Farmers Electric Cooperative, Inc.): Argued that Lea County Electric transferred its PURPA obligation to Western Farmers Electric, its "all-requirements provider." Denied that the transfer required Resolute Wind's consent and claimed to have a full-requirements contract with Western Farmers Electric. Denied that PURPA preempts Rule 570 and agreed that the parties dispute the application of avoided costs and their calculation method (para 14).

Legal Issues

  • Whether the New Mexico Public Regulation Commission (the Commission) erred in summarily dismissing Resolute Wind's complaint in the face of disputed issues of material fact (para 1).
  • Whether the Commission erred in relying on a federal agency’s determination in an earlier, unrelated matter to dismiss the complaint (para 2).

Disposition

  • The Supreme Court of the State of New Mexico annulled and vacated the final order appealed from and remanded the case to the Commission for further proceedings (para 33).

Reasons

  • The Supreme Court found that the Commission's summary dismissal of Resolute Wind's complaint violated procedural due process rights and was arbitrary, capricious, or an abuse of discretion. The Court highlighted that contested proceedings, whether judicial or administrative, cannot be subject to summary disposition in the presence of disputed material facts. The Commission's reliance on a federal agency's determination in an unrelated matter to dismiss the complaint was also deemed erroneous. The procedural and substantive missteps by the Commission, whether considered separately or together, necessitated the annulment and vacating of the final order, with a remand for further proceedings to allow all parties an opportunity to present evidence in support of their positions (paras 1-2, 21-32).