Facts

  • Echo and Enduro were parties to a joint operating agreement (JOA) involving a new drilling project. Under the JOA, Echo, proposing the project, had to notify other parties, allowing them 30 days to opt in or out. Enduro opted out, becoming "non-consenting" and thus not responsible for costs or risks but also not entitled to profits until consenting parties recovered 400% of the project's costs. The JOA required that for consenting parties to keep non-consenting parties' share of profits, they must commence the operation within 120 days of proposal. Echo did not obtain a drilling permit within this period but engaged in various preparatory activities. The dispute centered on whether these activities constituted the commencement of drilling operations under the JOA.

Procedural History

  • District Court: Granted summary judgment in favor of Echo.
  • Court of Appeals: Reversed the district court's decision, granting summary judgment in favor of Enduro and remanded for entry of summary judgment in Enduro's favor.

Parties' Submissions

  • Echo: Argued that its preparatory activities, including surveying, staking, consulting, and entering into contracts, demonstrated a good-faith intent to diligently carry on drilling activities, thus satisfying the JOA's requirement to commence operations.
  • Enduro: Contended that Echo's lack of on-site activity and failure to obtain a drilling permit evidenced that Echo had not actually commenced drilling operations as required by the JOA.

Legal Issues

  • Whether activities undertaken by Echo satisfied the JOA's requirement to "actually commence" drilling operations within the specified timeframe.
  • Whether the failure to obtain a drilling permit within the commencement period is dispositive of whether a party has commenced drilling operations.

Disposition

  • The Supreme Court reversed the Court of Appeals and held that the failure to obtain an approved drilling permit within the relevant commencement period is not dispositive. The Court remanded the case for further proceedings consistent with its opinion.

Reasons

  • The Supreme Court, per Justice Edward L. Chávez, found that a party may prove commencement of drilling operations with evidence of committed resources demonstrating a present good-faith intent to diligently carry on drilling activities until completion, even without an approved drilling permit (paras 3, 11). The Court clarified that actual drilling is not necessary for commencement, and activities such as entering into an enforceable drilling contract can suffice as evidence of commencement (paras 6-10, 26). The Court disagreed with the Court of Appeals' emphasis on the necessity of a drilling permit for commencement, distinguishing the purposes of the JOA from regulatory requirements (paras 11-15). The Court identified a genuine issue of material fact regarding whether Echo and JW Drilling entered into a binding contract before the deadline, necessitating resolution by a factfinder (paras 27-28). The Court also addressed the premature award of attorneys' fees by the Court of Appeals, noting that such an award was inappropriate while a writ of certiorari was pending (para 29).
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.