Facts

  • The case involves an appeal by New Energy Economy, Inc. (NEE) against the New Mexico Public Regulation Commission (PRC) concerning the approval of a contested stipulation that granted the Public Service Company of New Mexico (PNM) certificates of public convenience and necessity (CCNs) to acquire new generation resources. The appeal also addressed the PRC's proposal to dismiss protests to PNM’s 2014 integrated resource plan (IRP). The core of the dispute centered on the PRC's decision-making process, the evaluation of alternative energy resources, and the procedural handling of PNM's applications and stipulations related to the retirement and replacement of San Juan Generating Station Units 2 and 3 (paras 1, 3-10).

Procedural History

  • [Not applicable or not found]

Parties' Submissions

  • Appellant (NEE): Argued that the PRC violated New Mexico law by approving the contested stipulation and by proposing to dismiss protests to PNM's 2014 IRP. Contended that the PRC's decision was based on a mistaken understanding of the law and factual assertions that were rejected below (para 1).
  • Appellee (PRC) and Intervenors-Appellees (PNM, New Mexico Industrial Energy Consumers, and Western Resource Advocates): Defended the PRC's final order and the process leading to the approval of the contested stipulation. Argued that the stipulation and the dismissal of protests were in accordance with statutory and regulatory standards (paras 11-44).

Legal Issues

  • Whether the PRC's order approving the contested stipulation and proposing to dismiss protests to PNM's 2014 IRP violated New Mexico statutes and regulations (para 11).
  • Whether the PRC's decision-making process and evaluation of alternative energy resources were conducted properly and in the public interest (paras 29-44).

Disposition

  • The Supreme Court of the State of New Mexico affirmed the PRC’s final order (para 46).

Reasons

  • The Supreme Court found that the PRC's decision was supported by substantial evidence and was a lawful exercise of discretion. The Court determined that the PRC and the hearing examiner (HE) correctly applied statutory and regulatory standards in approving the contested stipulation and in proposing to dismiss the protests to PNM's 2014 IRP. The Court rejected NEE's arguments, including claims of improper burden shifting, failure to consider renewable resources adequately, and the assertion that the PRC removed or postponed its oversight. The Court emphasized that the PRC's final order and the process leading to it were in the public interest, providing a net public benefit by addressing federal haze standards compliance, reducing emissions, and incorporating future renewable energy production. The decision was based on a comprehensive review of the administrative record, expert testimony, and the stipulation's provisions aimed at mitigating ratepayer risks and ensuring cost-effective energy resource planning (paras 11-45).