Facts

  • Plaintiff Sunnyland Farms, Inc. purchased a commercial greenhouse operation with the intention of hydroponically growing tomatoes. Before planting its first crop, the facilities were destroyed by fire. Plaintiff alleged that the fire could not be effectively fought due to Defendant Central New Mexico Electric Cooperative, Inc.'s failure to provide advance notice before disconnecting electric power, which prevented access to water necessary for extinguishing the fire.

Procedural History

  • District Court: Awarded Plaintiff approximately $21 million in consequential damages and $100,000 in punitive damages, attributing 80% fault to Plaintiff and 20% to Defendant on the negligence claim. The court did not consider Plaintiff’s fault on the breach of contract claim and permitted Plaintiff to elect its remedy after the appeal period expired.
  • Court of Appeals: Reversed the award of consequential and punitive damages on the contract claim, and the award of future lost profits on the negligence claim. Affirmed the district court on all issues raised in Plaintiff's cross-appeal.

Parties' Submissions

  • Plaintiff: Argued that Defendant's failure to provide advance notice of power disconnection was a breach of contract and negligence, leading to the inability to access water to fight the fire, resulting in substantial damages.
  • Defendant: Contended that the district court erred in awarding consequential damages for breach of contract, in awarding punitive damages, and in the calculation of lost profits, arguing that Plaintiff's evidence lacked reasonable certainty.

Legal Issues

  • Whether the district court erred in awarding consequential damages for breach of contract.
  • Whether the district court erred in awarding punitive damages.
  • Whether the district court erred in its calculation of lost profits awarded on Plaintiff’s negligence claim.
  • Whether the district court erred in not awarding prejudgment interest and in allowing a set-off against the judgment.

Disposition

  • The award of consequential damages for breach of contract and punitive damages was reversed.
  • The award of future lost profits on the negligence claim was reversed.
  • The district court's decisions on not awarding prejudgment interest and allowing a set-off against the judgment were affirmed.

Reasons

  • The Court of Appeals found that the district court's award of consequential damages in contract and punitive damages was not supported by the evidence and did not meet the required legal standards (paras 1-118).
    The Court determined that the Plaintiff's evidence for future lost profits lacked reasonable certainty, making the award unsupported by sufficient evidence (paras 89-99).
    The Court held that the district court did not abuse its discretion in refusing to award prejudgment interest and in allowing a set-off against the judgment, as there was no legal basis to preclude the set-off and no persuasive rationale for awarding prejudgment interest under the circumstances (paras 102-118).