Ontario Energy Board

Decision Information

Summary:

Union Gas Limited (Union) filed an application with the Ontario Energy Board (OEB) on June 10, 2016 for:
1. leave to construct 40 kilometres of 36 inch diameter pipeline from Union’s Dawn Compressor Station in the Township of Dawn-Euphemia to its Dover Transmission Station in the Municipality of Chatham-Kent (the Project) pursuant to section 90 of the Ontario Energy Board Act, 1998, S.O. 1998, c.15, Schedule B (Act)
2. approval of the recovery of costs associated with the construction of the Project pursuant to section 36 of the Act
3. approval to calculate the Project’s revenue requirement and resulting rates based on a 20 year depreciation term
4. approval of an accounting order to establish a Panhandle Reinforcement Deferral Account pursuant to section 36 of the A