Summary:

Union Gas Limited (Union) applied to the Ontario Energy Board (OEB) on January 7, 2016 under section 90 of the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, Schedule B (the OEB Act) for approval to relocate and replace two existing pipelines (the Project). The Project is needed to accommodate the Windsor Detroit Bridge Authority’s (WDBA) International Detroit River Crossing Project in the City of Windsor, and in particular the construction of a new customs and immigration plaza

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.