Ontario Energy Board
Decision Information
Enbridge Gas Distribution Inc. (Enbridge) applied with the Ontario Energy Board (OEB) on June 30, 2015 under section 90(1) of the Ontario Energy Board Act, 1998 (the Act) for leave to construct 8.9 kilometres of 6 inch diameter natural gas pipeline and ancillary facilities (Project) to serve the Canadian Nuclear Laboratory Chalk River Facility (CNL) in the Town of Laurentian Hills, County of Renfrew. The Pipeline route is located in the Towns of Deep River and Laurentian Hills in the County of Renfrew. The construction is planned to start by January 2016. The planned in-service date is October 2016. The proposed route runs along municipal road allowances, private lands and lands of the Department of National Defence (DND).