Résumé :
Having considered and weighed all of the evidence before it, the National Energy Board (NEB or the Board) finds that the Bakken Pipeline Project Canada (the Project), as proposed by Enbridge Bakken Pi...
Résumé :
The National Energy Board (NEB or Board) has considered the evidence and submissions made by all Participants in the MH-001-2017 proceeding. The Board’s views and conclusions on the matters that fall...
Résumé :
On 8 August 2011, Enbridge applied under section 58 of the National Energy Board Act (NEB Act) to reverse the approximately 194 km long segment of Line 9 between Sarnia Terminal (SA) and North Westove...
Résumé :
The National Energy Board (Board) recommends that a Certificate of Public Convenience and Necessity (Certificate) be issued for the Section 52 Facility of the Enbridge Pipelines Inc. (Enbridge) Edmont...