26.Résumé : Le 19 mai 2016, l’Office national de l’énergie a publié un rapport recommandant au gouverneur en conseil d’agréer le projet d’agrandissement du réseau de Trans Mountain (le « projet »), sous réserve d...
-
27.Résumé : L’Office national de l’énergie a examiné la demande susmentionnée, datée du 16 août 2017, qui décrit les travaux de cessation d’exploitation du pipeline Petrolia, faisant 134 m de long, et des install...
-
28.Résumé : On 19 May 2016, the National Energy Board (NEB or Board) issued its Report recommending that Governor in Council approve the Trans Mountain Expansion Project (TMEP), subject to 157 conditions (A77045)...
-
29.Résumé : On 19 May 2016, the National Energy Board (NEB or Board) issued its Report recommending that Governor in Council approve the Trans Mountain Expansion Project (TMEP), subject to 157 conditions (A77045)...
-
30.Résumé : On 19 May 2016, the National Energy Board (NEB or Board) issued its Report recommending that Governor in Council approve the Trans Mountain Expansion Project (TMEP), subject to 157 conditions (A77045)...
-
31.Résumé : Le 30 juin 2017, M&NP a présenté à l’Office national de l’énergie une demande aux termes de la partie IV de la Loi sur l’Office national de l’énergie et des Lignes directrices révisées relatives aux r...
-
32.Résumé : L’Office national de l’énergie réglemente les pipelines pendant tout leur cycle de vie, dès la construction et pendant l’utilisation jusqu’à la cessation d’exploitation.
L’alinéa 74(1)d) de la Loi su...
-
33.
Trans Mountain Pipeline ULC (Trans Mountain) (Re) - 2018-03-01
National Energy Board - Décision [ Anglais ]Résumé : On 19 May 2016, the National Energy Board (NEB or Board) issued its Report recommending that Governor in Council approve the Trans Mountain Expansion Project (TMEP), subject to 157 conditions (A77045)...
-
34.Résumé : L’Office national de l’énergie a examiné la demande susmentionnée, datée du 21 août 2017. En vertu de l’alinéa 74(1)d) de la Loi sur l’Office national de l’énergie (la « Loi »), l’Office a rendu l’ord...
-
35.Résumé : Le 19 mai 2016, l’Office national de l’énergie a publié un rapport recommandant au gouverneur en conseil d’agréer le projet d’agrandissement du réseau de Trans Mountain (le « projet »), sous réserve d...
-
36.Résumé : Le 19 mai 2016, l’Office national de l’énergie a publié un rapport recommandant au gouverneur en conseil d’agréer le projet d’agrandissement du réseau de Trans Mountain (le « projet »), sous réserve d...
-
37.
Trans Mountain Pipeline ULC (Trans Mountain) (Re) - 2018-02-15
National Energy Board - Décision [ Anglais ]Résumé : On 19 May 2016, the National Energy Board (NEB or Board) issued its Report recommending that Governor in Council approve the Trans Mountain Expansion Project (TMEP), subject to 157 conditions (A77045)...
-
38.
Trans Mountain Pipeline ULC (Trans Mountain) (Re) - 2018-02-06
National Energy Board - Décision [ Anglais ]Résumé : On 19 May 2016, the National Energy Board (NEB or Board) issued its Report recommending that Governor in Council approve the Trans Mountain Expansion Project (TMEP), subject to 157 conditions (A77045)...
-
39.
Trans Mountain Pipeline ULC (Trans Mountain) (Re) - 2018-02-06
National Energy Board - Décision [ Anglais ]Résumé : On 19 May 2016, the National Energy Board (NEB or Board) issued its Report recommending that Governor in Council approve the Trans Mountain Expansion Project (TMEP), subject to 157 conditions (A77045)...
-
40.
Trans Mountain Pipeline ULC (Trans Mountain) (Re) - 2018-02-06
National Energy Board - Décision [ Anglais ]Résumé : On 19 May 2016, the National Energy Board (NEB or Board) issued its Report recommending that Governor in Council approve the Trans Mountain Expansion Project (TMEP), subject to 157 conditions (A77045)...
-
41.
Trans Mountain Pipeline ULC (Trans Mountain) (Re) - 2018-02-06
National Energy Board - Décision [ Anglais ]Résumé : On 19 May 2016, the National Energy Board (NEB or Board) issued its Report recommending that Governor in Council approve the Trans Mountain Expansion Project (TMEP), subject to 157 conditions (A77045)...
-
42.Résumé : The National Energy Board (NEB or Board) has considered the evidence and submissions made by all Participants in the MH-001-2017 proceeding. The Board’s views and conclusions on the matters that fall...
-
43.
Maritimes & Northeast Pipeline Management Ltd. (M&NP) (Re) - 2018-01-22
National Energy Board - DécisionRésumé : Le 17 novembre 2016, Maritimes & Northeast Pipeline Management Ltd. (« M&NP » ou la « société ») a présenté une demande à l’Office national de l’énergie aux termes de la partie IV de la Loi sur l’Offi...
-
44.Résumé : Le présent rapport de l’Office national de l’énergie (le « rapport ») renferme la décision rendue par l’Office, ainsi que les motifs, relativement à la demande présentée par Trans Mountain Pipeline UL...