1.Summary: On 26 May 2015, A C LNG Inc. (A C LNG or Applicant) applied to the National Energy Board (NEB or Board) pursuant to section 117 of the National Energy Board Act (NEB Act) for a licence (Export Licence...
-
2.
-
3.Summary: In early 2008, the National Energy Board (Board or NEB) identified a proposed approach for the Land Matters Consultative Initiative (LMCI), consisting of four distinct topic streams. One of the stream...
-
4.
-
5.Summary: The Alliance Pipeline (Pipeline) has been in commercial operation since December 2000. North American gas markets have changed considerably in the years since the Pipeline was first commissioned. As a...
-
6.Summary: Alliance Pipeline Ltd. (Alliance) Compliance Filing on Interruptible and Seasonal Bid Mechanics dated 7 October 2015
Alliance Application for Approval of New Services and related Tolls and Tariffs for...
-
7.Summary: On 29 October 2015, the Board issued a letter to all interested persons, informing them that the Board would commence its review of all NEB-regulated pipeline companies’ ACEs. This notification provid...
-
8.
-
9.Summary: On 1 June 2015, AltaGas DCLNG applied to the National Energy Board (NEB or Board) pursuant to section 117 of the National Energy Board Act (NEB Act) for a licence to export natural gas (Licence) in th...
-
10.Summary: The National Energy Board (NEB or Board) has considered the above-referenced application dated 16 March 2016 (Application). Pursuant to paragraph 74(1)(d) of the National Energy Board Act (NEB Act),...
-
11.Summary: On 11 February 2016, AltaGas LPG General Partner Inc. on behalf of AltaGas LPG Limited Partnership (AltaGas LPG) applied to the National Energy Board (NEB or Board) pursuant to section 117 of the Nati...
-
12.Summary: We have decided to issue a Licence to Aurora LNG, subject to the approval of the Governor in Council, to export natural gas with the terms and conditions described in Appendix I to this letter. Our ro...