National Energy Board

Decision Information

Summary:

On 25 March 2013, Forty Mile filed its Application to abandon the Canadian portion of its Gas Distribution System constructed under the authority of Order XG-F73-4-98, at a total estimated cost of $1,500 (Project). Supplemental information about environmental and engineering matters was received by the Board on 13 August 2013, from Forty Mile in its response to the Board’s Information Request No.1.

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.