1.1 Application and Project Overview
On 15 December 2017, NGTL applied to the National Energy Board (Board or NEB) pursuant to section 58 of the NEB Act, for authorization to construct and operate the Project, which includes 23 kilometres (km) of new pipeline within Clear Hills County, Alberta (Application).