Summary:

This National Energy Board Report (Report) constitutes the National Energy Board’s (NEB or Board) decision and reasons in respect of the Trans Mountain Pipeline ULC (Trans Mountain) application pursuant to section 21 of the National Energy Board Act (NEB Act) seeking a variance to Certificate of Public Convenience and Necessity OC-064 (Certificate). The Chilliwack BC Hydro Route Realignment (Chilliwack Realignment) would change the general pipeline corridor of the Trans Mountain Expansion Project (TMEP) for a short section and would relocate the TMEP to be within the existing Trans Mountain pipeline (TMPL) right-of-way. The realignment is outside the approved TMEP corridor for approximately 1.8 kilometres (km).

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.