Summary:

On 24 March 2017, NGTL applied to construct and operate the Project pursuant to section 58 of the National Energy Board Act (NEB Act) and section 45.1 of the National Energy Board Onshore Pipeline Regulations (OPR) (Application). In the Application, NGTL also requested exemptions from paragraph 30(1)(a) and section 31 of the NEB Act.

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.