National Energy Board

Decision Information

Summary:

The National Energy Board (NEB or Board) has considered the above-referenced application dated 22 September 2017 (Application). The Application describes activities related to the Chinook-Loomis Pipeline and associated facilities (Facilities). Pursuant to paragraph 74(1)(d) of the National Energy Board Act (NEB Act), and taking into account section 50 of the National Energy Board Onshore Pipeline Regulations (OPR), the Board has issued the attached Order ZO-M182-001-2018 (Order), the effect of which is to grant (MIPL(C)L) leave to abandon the Facilities. The attached Order sets out the conditions the Board has imposed on the Project.

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.