National Energy Board

Decision Information

Summary:

NOVA Gas Transmission Ltd. (NGTL, Applicant or Company) applied to the National Energy Board (Board or NEB), for leave to purchase the Albersun Pipeline from Suncor Energy Logistics Corporation (Suncor) pursuant to paragraph 74(1)(b) of the National Energy Board Act (Act or NEB Act) and for the Board to issue a report recommending the issuance of a Certificate, pursuant to section 52 of the NEB Act, for the continued operation of the Albersun Pipeline. The proposed acquisition and continued operation of approximately 179 km of pipeline, plus associated mainline valves, launcher and receiver facilities, metering facilities and rights-of-way (ROWs). After Closing, NGTL will physically isolate the Albersun Pipeline in the Crow Lake area from the CNRL-owned, southern portion of the pipeline. No further construction, decommissioning or abandonment activities associated with the Albersun Pipeline are proposed by NGTL (Project).

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.