135.Summary: On 12 August 2013, TransCanada PipeLines Limited (TransCanada) filed the Review Application with the National Energy Board. TransCanada requested, among other things, that the Board rescind Hearing Or...
-
136.Summary: This letter provides the Board’s reasons for its 19 August 2013 decision on the Review Applicationand for adjusting the timetable of events to allow for the start of the oral portion of the MH-002-201...
-
137.Summary: On 17 June 2013, TransCanada filed the Tariff Amendment Application under Part I and Part IV
of the National Energy Board Act1 (NEB Act). In the Tariff Amendment Application,...
-
138.Summary: TransCanada filed the Tariff Amendment Application following the release of the National Energy Board’s (Board) RH-003-2011 Decision. Most of the proposals made in the Tariff Amendment Application wer...
-
139.Summary: On 20 December 2013, TransCanada filed an application for approval of a settlement agreement (Settlement) for its Mainline System (Mainline). The existing tolls and tariff for the TransCanada Mainline...
-
140.Summary: On 20 December 2013, TransCanada filed an application for approval of a settlement agreement (Settlement) for its Mainline System (Mainline). The existing tolls and tariff for the TransCanada Mainlin...
-
141.Summary: On 10 November 2015, TransCanada applied to the National Energy Board (NEB or Board) for an order from the Board granting approval to construct and operate the Project pursuant to section 58 of the Na...
-
142.Summary: On 10 November 2015, TransCanada applied to the National Energy Board (NEB or Board) for an order from the Board granting approval to construct and operate the Project pursuant to section 58 of the Na...
-
143.Summary: Over the past five years, market circumstances and tolling on the TransCanada Mainline Pipeline System (Mainline) have evolved significantly. In the RH-003-2011 proceeding, the National Energy Board (...
-
144.Summary: On 25 February 2015, the National Energy Board (Board or NEB) received an application from TransCanada (the Application) for the Project.
-
145.
TransCanada PipeLines Limited (TransCanada) (Re) - 2015-06-02
National Energy Board - Decision and OrderSummary: On 15 August 2014, TransCanada applied to the National Energy Board (NEB or Board) for an Order from the Board granting approval to construct and operate the Project pursuant to section 58 of the Nati...
-
146.Summary: On 30 November 2016, the National Energy Board (Board) received TransCanada’s Notice of Intent to File an Application for the Herbert LTFP service. The Board established a modified version of the Stre...
-
147.Summary: On 30 November 2016, the National Energy Board (Board) received TransCanada’s Notice of Intent to File an Application for the Herbert LTFP service. On 20 December 2016, the Board established a modifie...
-
148.Summary: On 29 March 2017, the National Energy Board (Board) received TransCanada’s Notice of Intent to File an Application for an order approving a new long-term fixed price service from Empress, Alberta to D...
-
149.Summary: In the RH-001-2014 Reasons for Decision, the National Energy Board (Board) approved the components of the Mainline 2013-2030 Settlement Agreement (Settlement) reached between TransCanada and its three...
-
150.Summary: We have decided to issue a licence to Triton LNG Inc. on behalf of Triton LNG Limited
Partnership, subject to the approval of the Governor in Council, to export natural gas with the terms and conditio...