Manitoba Public Utilities Board

Decision Information

Summary:

By this Order, the Manitoba Public Utilities Board (“Board”) varies a prior Order and imposes an administrative monetary penalty of $35 per day on Centra Gas Manitoba Inc. (“Centra”) for its default in filing a General Rate Application as required by Order 108/15 Directive 12. The penalty commences as of July 20, 2018 and continues until the day the
Board receives Centra’s General Rate Application. In reaching this decision the Board reviewed Centra’s submission in response to Order 95/18 Directive 2 and Section 100 of The Public Utilities Board Act which permits a maximum penalty of $100 per day.

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.