Manitoba Public Utilities Board

Decision Information

Summary:

By this Order, the Public Utilities Board (Board) approves the July 14, 2017 interim ex parte Application of Centra Gas Manitoba Inc. (Centra) for a revised Primary Gas rate effective August 1, 2017. Additionally, the Board approves the revised interim nonPrimary Gas rates for all customer classes except the Special Contract and Power Station classes. The revised interim non-Primary Gas costs are as a result of the Board’s Directive 5 in Order 108/15. In respect of Centra’s Application and by this Order:

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.