British Columbia Utilities Commission

Decision Information

Summary:

On April 30, 2012, the British Columbia Utilities Commission (Commission) issued Order C-6-12 and the accompanying
Reasons for Decision granting a Certificate of Public Convenience and Necessity (CPCN) to FortisBC Energy Inc. (FEI) for constructing and operating a Compressed Natural Gas (CNG) refueling station at BFI Canada Inc. (BFI). Directive 3. of Order C-6-12 directed FEI to establish two new service classes, one for CNG service and one for Liquefied Natural Gas (LNG) service;

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.