Summary:

FortisBC Energy Inc. (FEI) was granted approval by the British Columbia Utilities Commission (Commission) for the Muskwa River Crossing project by Order G-27-11, dated February 24, 2011. The Commission specifically approved the method of attaching a pipeline to the Muskwa River highway crossing at a project cost of $3,015,650. Subsequent to that Order FEI was not able to obtain the necessary approvals from the Public Works and Government Services Canada to attached the pipeline to the Muskwa River highway bridge and other alternatives FEI considered would exceed the previous cost estimate;