Summary:

On September 14, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to sections 59 to 61 and section 89 of the Utilities Commission Act (UCA), for interim and permanent approval and endorsement of a Rate Schedule 11B Tariff Supplement No. K-1, a Biomethane Long Term Large Volume Interruptible Sales Agreement (Tariff Supplement No. K-1 or Agreement), effective October 1, 2017 (Application), filed as Appendix A of the Application;

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.