British Columbia Utilities Commission

Decision Information

Summary:

On December 12, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to sections 59 to 61 and 89 of the Utilities Commission Act (UCA), for approval of the rates established in the Fueling Equipment Licence and Use Agreement between FEI and United Parcel Service Canada Ltd. (UPS) (UPS Agreement) on an interim basis, effective January 5, 2018 (Application);

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.