Summary:

On September 16, 2016, by Decision and Order G-147-16, the British Columbia Utilities Commission (Commission) approved, pursuant to sections 29, 30 and 59 to 61 of the Utilities Commission Act, FortisBC Energy Inc.’s (FEI) mains extension test, customer connection policies and related reporting requirements. In Order G-147-16, FEI was directed to file black-line changes to its General Terms and Conditions consistent with the Decision within 30 days;

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.