Summary:
On December 30, 2015, the British Columbia Utilities Commission (Commission) issued Order G-215-15 and accompanying Reasons for Decision regarding Corix Multi-Utility Services Inc.’s (Corix) Application for a Certificate of Public Convenience and Necessity (CPCN) for Additional Capital and Amended Rates for UniverCity Neighbourhood Utility Service (NUS) on Burnaby Mountain. As part of Corix’s application, it proposed to replace and expand the capacity of the existing temporary natural gas facilities with a larger capacity natural gas boiler plant (Project);
Decision Content
You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.