Summary:
By Order G-72-07 dated July 5, 2007, the British Columbia Utilities Commission (Commission) approved Participant Assistance/Cost Award (PACA) Guidelines, included as Appendix A to the Order. Pursuant ...
Summary:
On September 15, 2014, the British Columbia Utilities Commission (Commission) issued Order G-139-14 along with its Reasons for Decision (the PBR Decision) approving for FortisBC Inc. (FBC) a Multi-Yea...
Summary:
On March 28, 2013, FortisBC Inc. (FortisBC) filed an application with the British Columbia Utilities Commission (Commission) for approval of new rates for transmission voltage customers which included...
Summary:
On November 10, 2016, FortisBC Inc. (FBC) filed with the British Columbia Utilities Commission (Commission) its Self-Generation Policy Stage II Application, seeking among other things, approval of the...
Summary:
On November 20, 2017, FortisBC Inc. (FBC) filed with the British Columbia Utilities Commission (Commission) an application for approval to amend Electric Tariff Rate Schedule 50 Lighting - All Areas (...
Summary:
FortisBC Inc. (FBC) submitted its 2016 Long Term Electric Resource Plan (LTERP) and Long Term Demand-Side Management (DSM) Plan (LTDSM Plan) Application (2016 LTERP & LTDSM Plan, Application) in Novem...
Summary:
On November 15, 2017, FortisBC Inc. (FBC) submitted its application for acceptance of 2018 Demand-Side Management (DSM) Expenditures (Application) pursuant to section 44.2 of the Utilities Commission ...