ATCO Gas and Pipelines Ltd. (ATCO), by Application 23952-A001 registered on October 2, 2018, filed an application with the Alberta Utilities Commission under Section 12 of the Pipeline Act and Section 4.1 of the Gas Utilities Act for the following:
• length amendment of line 135 from 0.01 kilometres to 0.02 kilometres
• length amendment of line 138 from 0.57 kilometres to 0.41 kilometres
• length amendment of line 158 from 0.27 kilometres to 0.42 kilometres
• status amendment of line 139 from abandoned to removed
• mapping amendment of lines 135, 138 and 158

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.