Decision Information
On September 22, 2016, ATCO Pipelines, a division of ATCO Gas and Pipelines Ltd., filed an application with the Alberta Utilities Commission requesting approval of its 2017-2018 general rate application (GRA). This application was addressed through a full written process that included two rounds of information requests (IRs), argument and reply argument (the original proceeding). On August 29, 2017, the Commission issued Decision 22011-D01-20171 where, at paragraph 636 of the decision, the Commission directed ATCO Pipelines to file a compliance application in accordance with the findings and directions of the decision by October 11, 2017. ATCO Pipelines filed its compliance application on October 2, 2017. In its compliance application, ATCO Pipelines requested approval and/or confirmation of: