Alberta Utilities Commission
Decision Information
Summary:
ATCO Gas and Pipelines Ltd. (ATCO), by Application 23016-A001 registered on October 11, 2017, filed an application with the Alberta Utilities Commission under Section 11 of the Pipeline Act and Section 4.1 of the Gas Utilities Act to remove a compressor installation, installation 009, near Blackfoot. The proposed work is related to the minor removal of an existing pipeline installation, within the original site, previously constructed and operating in accordance with approvals granted in Licence 25935.
Decision Content
You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.