Alberta Utilities Commission

Decision Information

Summary:

AltaGas Utilities Inc. (AltaGas), by Application 22832-A001 registered on July 27, 2017, filed an application with the Alberta Utilities Commission under Section 12 of the Pipeline Act and Section 4.1 of the Gas Utilities Act to reflect the amended maximum operating pressure of lines 61, 62, 63 and 64 of Licence 1055 from 9,650 kilopascals to 4,830 kilopascals and reflect the reversal of the flow direction of these lines in the Calmar area. The proposed amendments are related to facilities previously constructed and operating in accordance with approvals granted in Licence 1055.

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.