Alberta Utilities Commission

Decision Information

Summary:

ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application 22496-A001, registered on March 24, 2017, filed an application with the Alberta Utilities Commission under Section 12 of the Pipeline Act and Section 4.1 of the Gas Utilities Act for the following in the city of Calgary:
-splitting of line 13 into lines 13, 37 and 38
- reinstatement of a portion of original line 13, previously approved to be removed, as abandoned line 37
- the pipe status of line 13 is to remain as “removed”
- pipe status amendment of line 12 from operating to abandoned
- length amendment of line 4 from 0.18 kilometres (km) to the revised length of 0.06 km
- length amendment of line 12 from 0.15 km to the revised length of 0.24 km
- mapping amendment of lines 4, 12, 13 and 14

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.