ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application 22398-A001, registered on February 7, 2017, filed an application with the Alberta Utilities Commission under Section 12 of the Pipeline Act and Section 4.1 of the Gas Utilities Act for the following:
length amendment of lines 176 and 177
splitting of line 176 into lines 176, 202 and 203
outside diameter amendment of lines 160 to 165 and lines 168 to 193 from 609.6 millimetres to 610 millimetres