Summary:

ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application 21923-A001 registered on August 24, 2016, filed an application with the Alberta Utilities Commission under Section 11 of the Pipeline Act and Section 4.1 of the Gas Utilities Act to remove the Hinton Compressor Station (installation 3 of Licence 625). The proposed work is related to the minor removal of an existing pipeline installation, within the original lease, previously constructed and operating in accordance with approvals granted in Licence 625.

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.