Alberta Utilities Commission
Decision Information
Summary:
ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application 21407-A001 registered
on March 7, 2016, filed an application with the Alberta Utilities Commission under Section 12 of the Pipeline Act and Section 4.1 of the Gas Utilities Act to reinstate a pipeline segment, previously approved to be removed, as abandoned line 171. The proposed amendment is related to facilities previously constructed in accordance with approvals granted in Licence 2027.
Decision Content
You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.