Summary:
ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application 21449-A001 registered on March 22, 2016, filed an application with the Alberta Utilities Commission under Section 12 of the Pipeline Act and Section 4.1 of the Gas Utilities Act for the following in the Fort McMurray area:
length amendment of line 14 from 0.22 kilometres to 0.28 kilometres
“To Location” LSD amendment of line 14 from “4” to “5”
mapping amendment of line 14
Decision Content