The Alberta Electric System Operator (AESO) filed an application with the
Alberta Utilities Commission, pursuant to Section 34 of the Electric Utilities Act, for approval of the need to connect the Enbridge Pipelines Inc. (Enbridge) Battle Sands 594S substation to the 138-kilovolt (kV) transmission system in the Hardisty area. The needs identification document application was registered on October 19, 2015, as Application 20932-A001.

Decision Content

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.