ATCO Pipelines (AP), a division of ATCO Gas and Pipelines Ltd., filed an application (the application) with the Alberta Utilities Commission on December 17, 2014, requesting approval of a monthly fixed fee, on an interim basis, of $17,724,000 per month, effective January 1, 2015. The requested interim revenue requirement reflected 100 per cent of AP’s forecast 2015 revenue requirement of $214.7 million. The Commission assigned Proceeding 3586 and Application 1611091-1 to the application.