51.Summary: On May 15, 2014, ATCO Gas and Pipelines Ltd. (ATCO Gas) submitted an application with the Alberta Utilities Commission (AUC or the Commission) notifying the Commission that the ATCO Gas North (AGN) we...
-
52.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610816 registered on September 3, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Sectio...
-
53.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610825 registered on September 8, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section...
-
54.Summary: On June 28, 2013, AltaGas Utilities Inc. (AUI) filed a 2013-2017 Performance-Based
Regulation (PBR) Phase II application (PBR Phase II application) with the Alberta Utilities Commission (AUC or the Co...
-
55.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610794 registered on August 22, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section ...
-
56.Summary: AltaGas Utilities Inc. (AltaGas) submitted its monthly filing on August 25, 2014, to the
Alberta Utilities Commission (the AUC or the Commission) for its proposed third party ...
-
57.Summary: AltaGas Utilities Inc. (AltaGas) submitted its monthly filing on August 25, 2014, with the Alberta Utilities Commission (the AUC or the Commission) for its proposed gas cost recovery1 rate (GCRR) for...
-
58.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610786 registered on August 14, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section 1...
-
59.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610745 registered on July 25, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section 11...
-
60.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610762 registered on
July 30, 2014, filed an application with the Alberta Utilities Commission (AUC or ...
-
61.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610763 registered on July 31, 2014, filed an application with the Alberta Utilities Commission (AUC or
the Commission) under Section 12...
-
62.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610731 registered on July 15, 2014, filed an application with the Alberta Utilities Commission (AUC or
the Commission) under Section 11...
-
63.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610765 registered on July 31, 2014, filed an application with the Alberta Utilities Commission (AUC or
the Commission) under Section 12...
-
64.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610764 registered on July 31, 2014, filed an application with the Alberta Utilities Commission (AUC or
the Commission) under Section 12...
-
65.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610749 registered on July 25, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section 11 ...
-
66.Summary: On April 25, 2014, ATCO Pipelines (ATCO), a division of ATCO Gas and Pipelines Ltd.
(South), filed an application with the Alberta Utilities Commission (AUC or the Commission) pursuant to Section 11 o...
-
67.Summary: AltaGas Utilities Inc. (AltaGas) submitted its monthly filing on July 25, 2014, with the
Alberta Utilities Commission (the AUC or the Commission) for its proposed gas cost recovery 1 rate (GCRR) for...
-
68.Summary: AltaGas Utilities Inc. (AltaGas) submitted its monthly filing on July 25, 2014, to the
Alberta Utilities Commission (the AUC or the Commission) for its proposed third party transportation rate (TPTR)...
-
69.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610751 registered on July 25, 2014, filed an application with the Alberta Utilities Commission (AUC or
the Commission) under Section 11...
-
70.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610737 registered on July 17, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section 12 ...
-
71.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610716 registered on July 9, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section 12 o...
-
72.Summary: ATCO Gas, a division of ATCO Gas and Pipelines Ltd.(ATCO Gas) filed an application
(compliance application) with the Alberta Utilities Commission (the Commission or the AUC)...
-
73.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610713 registered on July 8, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section 11 o...
-
74.Summary: AltaGas Utilities Inc. (AltaGas), by Application No. 1610710 registered on July 4, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section 11 of the Pipe...
-
75.Summary: On March 13, 2014, AltaGas Ltd. (AltaGas) filed an application with the Alberta Utilities Commission (AUC or Commission) pursuant to Section 41(1)(a) of the Gas Utilities Act Code of Conduct Regulatio...