26.Summary: AltaGas Ltd. (AltaGas), pursuant to Approval No. U2014-87,1 is the operator of a power plant designated as the Parkland gas-fired power plant, in the Stavely area.
-
27.Summary: AltaGas Utilities Inc. (AltaGas) submitted its monthly filing on October 27, 2014, to the Alberta Utilities Commission (the AUC or the Commission) for its proposed third party transportation rate (TPT...
-
28.Summary: AltaGas Utilities Inc. (AltaGas) submitted its monthly filing on October 27, 2014, with the Alberta Utilities Commission (the AUC or the Commission) for its proposed gas cost recovery rate (GCRR)1 for...
-
29.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610923 registered on October 17, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section ...
-
30.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610916 registered on October 15, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section ...
-
31.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610951 registered on October 24, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section ...
-
32.Summary: On June 10, 2014, ATCO Gas and Pipelines Ltd. (AG or ATCO Gas) filed an application with the Alberta Utilities Commission (the AUC or the Commission) seeking approval of its proposed interim distribut...
-
33.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610909 registered on October 9, 2014, filed an application with the Alberta Utilities Commission (AUC or
the Commission) under Section 1...
-
34.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610905 registered on October 9, 2014, filed an application with the Alberta Utilities Commission (AUC or
the Commission) under Section 1...
-
35.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610901 registered on October 7 2014, filed an application with the Alberta Utilities Commission (AUC or
the Commission) under Section 11...
-
36.Summary: On August 8, 2014, AltaGas Utilities Inc. (AltaGas or AUI) submitted an application to the Alberta Utilities Commission (AUC or Commission) requesting approval for annual adjustments to its unaccounte...
-
37.Summary: On August 20, 2014, ATCO Gas and Pipelines Ltd. (ATCO Gas) filed an application
with the Alberta Utilities Commission (Commission) requesting approval of its unaccounted-for gas (UFG) rate rider (Ride...
-
38.Summary: AltaGas Utilities Inc. (AltaGas), by Application No. 1610900 registered on October 7, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section 11 of the P...
-
39.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610888 registered on October 1, 2014, filed an application with the Alberta Utilities Commission (AUC or
the Commission) under Section 1...
-
40.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610875 registered on September 25, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Sectio...
-
41.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610856 registered on September 23, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Sectio...
-
42.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610872 registered on September 25, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Sectio...
-
43.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610845 registered on September 16, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Secti...
-
44.Summary: AltaGas Utilities Inc. (AltaGas) submitted its monthly filing on September 24, 2014, to
the Alberta Utilities Commission (the AUC or the Commission) for its proposed third party transportation rate (...
-
45.Summary: AltaGas Utilities Inc. (AltaGas) submitted its monthly filing on September 24, 2014, with the Alberta Utilities Commission (the AUC or the Commission) for its proposed gas cost recovery rate (GCRR)1 ...
-
46.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610843 registered on September 12, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Sectio...
-
47.Summary: On January 31, 2014, AltaGas Utilities Inc. (AUI) submitted an application to the Alberta Utilities Commission (AUC or Commission) requesting approval to implement a 2013 capital tracker deficiency ra...
-
48.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO) filed Application No. 1610472 with the
Alberta Utilities Commission (AUC or the Commission) on April 11, 2014, seeking approval for an amendment to Licence ...
-
49.Summary: ATCO Gas and Pipelines Ltd. (South) (ATCO), by Application No. 1610822 registered on September 4, 2014, filed an application with the Alberta Utilities Commission (AUC or the Commission) under Section...
-
50.Summary: On May 28, 2014, ATCO Gas and Pipelines Ltd. (ATCO Gas or AG) submitted an application to the Alberta Utilities Commission (the AUC or the Commission) requesting approval to recover its north and sout...